How much does a bathroom renovation in Dubai cost?
The cost depends on the existing condition, bathroom size, layout changes and your selected finishes. Waterproofing, pipework, concealed fittings, shower glass, ceiling works and ventilation can all affect the scope. Taps, toilets, vanities and accessories also vary considerably in price. We review your bathroom and preferences before preparing a quotation with the inclusions and exclusions clearly set out.
Can you convert my bathtub into a walk-in shower?
Often, yes. We first assess the existing drain, floor build-up, available space and shower entry. A completely flush threshold is not suitable for every apartment. The design should balance comfortable access, drainage and splash control rather than assume the same solution works in every bathroom.
Can I keep a bathtub and still have a comfortable shower?
That may be possible with a considered combined layout. At the Parkview Corner Residence in DIFC, we designed a soaking bath with a step and an extended shower enclosure. The right solution depends on your room dimensions and existing services.
Do you need to remove the existing bathroom tiles?
That depends on their condition, the proposed scope and the building’s requirements. Some buildings do not allow existing tiles to be removed. In these cases, preparing the existing surface and tiling over the old tiles may be the only permitted option—and can also be more economical. We assess the existing surface and preparation needed before recommending a suitable finishing system.
How long does a bathroom renovation take?
Realistically, a single, full bathroom renovation typically takes two to four weeks, depending on the agreed scope and site conditions. We confirm a programme after assessing building access and material availability. Layout changes, waterproofing, testing and curing periods, concealed fittings and made-to-measure glass all affect the sequence.
If existing tiles are removed and new waterproofing is applied, some buildings require a pond test. This may require access to the apartment below, so the cooperation and availability of its occupant can influence the timeline.
A new shower glass partition typically has a delivery time of 10–14 working days after the order is placed. Obtaining a work permit from your management company can also take up to two weeks. We factor these lead times into planning; permits and advance procurement may need to be arranged before on-site renovation begins.
Will my building require approvals?
Requirements differ between buildings and proposed works. We review the applicable management requirements, permitted working hours and any submissions or inspections needed before work begins. Changes to drainage, services or the layout should be discussed early.
Can you help with a small apartment bathroom?
Yes. Our completed projects include compact bathrooms in DIFC, Dubai Marina and Downtown Dubai. We consider shower shape, storage, vanity depth, mirror placement, lighting and door clearances together to make the room more comfortable to use.
Can you replace the water heater and improve ventilation at the same time?
These can be included in the agreed renovation scope. Opening up the bathroom is an opportunity to review the heater, pipework, ceiling access and extraction. We assess the existing systems before confirming suitable replacements or upgrades.